Night shift for John
Ross chaos
Dave
Savides
HUGE traffic
snarls on the John
Ross Highway will be
a thing of the past
next week as road
builders move to
working at night.
The decision was
announced at
Wednesday’s meeting
of the John Ross
Project Liaison
Committee.
Commuter and
constructor
frustration reached
red hot levels over
the past week as
long ‘stop/go’
queues formed during
resurfacing of the
old John Ross
Highway.
Drivers hurled abuse
at road workers, who
in turn, were at
risk from dangerous
drivers.
‘Responding to
safety concerns in
the light of areas
of advanced
deterioration, we
have an
R11,2-million budget
to resurface the old
road by the end of
December, using
emerging
contractors’ said a
spokesperson.
‘We tried at first
to keep two lanes
open but it became
too dangerous, with
long delays, queue
jumping and vehicles
- especially trucks
- speeding.
‘In fact, one of our
staff was struck by
a truck and
trailer.’
Proposed agenda
Subject to
sub-contractors
being able to get
their planning done
and the availability
of asphalt at night,
the ‘late shift’
should begin on
Sunday night.
‘It will entail
extra costs, such as
flood lighting,
while security at
night will be an
added risk,’ said
the spokesman.
‘On the positive
side, while work in
the day is only
possible from 9am to
3pm, outside of peak
traffic, at night
more hours will be
possible.’
The programme ahead
is as follows:
• The section from
the eSikhawini
robots to the Mondi
robots will be
surfaced at night
over the next two
weeks and will
entail a stop/go
system
• After this, the
Mondi to Alton
robots section will
be done, with all
John Ross traffic
having to re-route
between the Mondi
intersection via the
new Kraft Link
access road to
Ceramic Curve in
Alton
• Similarly, when
the section between
the Alton and CBD (Foskor)
robots is being
resurfaced, John
Ross traffic will be
diverted along
alternate routes.
HUGE traffic
snarls on the John
Ross Highway will be
a thing of the past
next week as road
builders move to
working at night.
The decision was
announced at
Wednesday’s meeting
of the John Ross
Project Liaison
Committee.
Commuter and
constructor
frustration reached
red hot levels over
the past week as
long ‘stop/go’
queues formed during
resurfacing of the
old John Ross
Highway.
Drivers hurled abuse
at road workers, who
in turn, were at
risk from dangerous
drivers.
‘Responding to
safety concerns in
the light of areas
of advanced
deterioration, we
have an
R11,2-million budget
to resurface the old
road by the end of
December, using
emerging
contractors’ said a
spokesperson.
‘We tried at first
to keep two lanes
open but it became
too dangerous, with
long delays, queue
jumping and vehicles
- especially trucks
- speeding.
‘In fact, one of our
staff was struck by
a truck and
trailer.’
Proposed agenda
Subject to
sub-contractors
being able to get
their planning done
and the availability
of asphalt at night,
the ‘late shift’
should begin on
Sunday night.
‘It will entail
extra costs, such as
flood lighting,
while security at
night will be an
added risk,’ said
the spokesman.
‘On the positive
side, while work in
the day is only
possible from 9am to
3pm, outside of peak
traffic, at night
more hours will be
possible.’
The programme ahead
is as follows:
• The section from
the eSikhawini
robots to the Mondi
robots will be
surfaced at night
over the next two
weeks and will
entail a stop/go
system
• After this, the
Mondi to Alton
robots section will
be done, with all
John Ross traffic
having to re-route
between the Mondi
intersection via the
new Kraft Link
access road to
Ceramic Curve in
Alton
• Similarly, when
the section between
the Alton and CBD (Foskor)
robots is being
resurfaced, John
Ross traffic will be
diverted along
alternate routes.